Renovations to the existing gymnasium plus a new 53,000 SF field house addition to accommodate a new gym, weight room, dance studios and new locker rooms.
Photo Gallery
b
b
b
b
b
Project Details
Project Information:
Asplundh Field House
Academy of the New Church
Bryn Athyn, PA
53,000 SF field house addition
Architect: The Klett Organization
Client Information:
Academy of the New Church
Bryn Athyn, PA
Contract Information:
Construction Budget: Unknown
Contract Amount: $6,500,000.
Final Amount: $7,000,000. due to Owner Changes
Original Completion Schedule: 12 month duration
Actual Completion Schedule: 12 months
Contract type: Competitively Bid – Lump Sum Agreement
Completed:
Two Phases completed over a 12 month schedule with final completion by December 1999